Port Everglades Master Plan Recommended Phasing Schedule

Project

START DATE – END DATE

People Mover – Phase 1

Task 1: Permitting

3rd quarter 2006 – 2nd quarter 2007

Task 2: Planning and Design

3rd quarter 2007 – 4th quarter 2008

Task 3: Construction

1st quarter 2009 – 4th quarter 2011

People Mover – Phase 2

Task 1: Permitting

1st quarter 2014 – 4th quarter 2014

Task 2: Planning and Design

1st quarter 2015 – 4th quarter 2016

Task 3: Construction

1st quarter 2017 – 4th quarter 2018