Plantation Master Plan Project Schedule

 

Task Name

START DATE – END DATE

Task 1 - Project Management

 

1.1 TAC Advisory Board

1st week March 2002 – 3rd week November 2002

1.2 CPDD Advisory Board

1st week March 2002 – 4th week October 2002

1.3 Project Management Programs

1st week March 2002 – 5th week October 2002

Task 2 - Public Involvement & Design Studio

 

2.0 Public, Board & Commission Meetings

1st week March 2002 – 3rd week October 2002

2.1 Stakeholder Interviews

1st week May 2002 – 2nd week May 2002

2.2 Public Kick-off/Community Preference Mtg.

2nd Week May 2002

2.3.1 Charrette

2nd Week May 2002

2.3.2 Design Studio

1st week May 2002 – 2nd week May 2002

2.4 Presentation of Draft Plans

3rd week May 2002 – 4th week May 2002

2.5 Public Involvement & Plan Report

5th week May 2002 – 4th week June 2002

2.6 Final Master Plan & Prototype Site Plan

1st week September 2002 – 4th week September 2002

2.7 Final Presentation

3rd week October 2002 – 1st week November 2002

Task 3 - Transportation Analysis & Subarea Mobility Study

1st week March 2002 – 2nd week September

Task 4 - Land Use/Infrastructure Analysis

3rd week March 2002 – 4th week June 2002

Task 5 - Market Analysis

1st week April 2002 – 2nd week July 2002

Task 6 - Conceptual Master Plan Alternatives

1st week May 2002 – 2nd week October 2002

Task 7 - Prototype Site Plans

1st week May 2002 – 4th week October 2002

Task 8 - Delivery of Work Products & Executive Summary