Task Name
|
START
DATE – END DATE |
|
Task 1 - Project Management |
|
|
1.1 TAC Advisory Board |
1st
week March 2002 – 3rd week November 2002 |
|
1.2 CPDD Advisory Board |
1st
week March 2002 – 4th week October 2002 |
|
1.3 Project Management Programs |
1st
week March 2002 – 5th week October 2002 |
|
Task
2 - Public Involvement & Design Studio |
|
|
2.0 Public, Board & Commission
Meetings |
1st
week March 2002 – 3rd week October 2002 |
|
2.1 Stakeholder Interviews |
1st
week May 2002 – 2nd week May 2002 |
|
2.2 Public Kick-off/Community Preference
Mtg. |
2nd
Week May 2002 |
|
2.3.1 Charrette |
2nd
Week May 2002 |
|
2.3.2 Design Studio |
1st
week May 2002 – 2nd week May 2002 |
|
2.4 Presentation of Draft Plans |
3rd
week May 2002 – 4th week May 2002 |
|
2.5 Public Involvement & Plan Report |
5th
week May 2002 – 4th week June 2002 |
|
2.6 Final Master Plan & Prototype
Site Plan |
1st
week September 2002 – 4th week September 2002 |
|
2.7 Final Presentation |
3rd
week October 2002 – 1st week November 2002 |
|
Task 3 - Transportation Analysis &
Subarea Mobility Study |
1st
week March 2002 – 2nd week September |
|
Task
4 - Land Use/Infrastructure Analysis |
3rd week March 2002 – 4th week June 2002 |
|
Task 5 - Market Analysis |
1st
week April 2002 – 2nd week July 2002 |
|
Task 6 - Conceptual Master Plan
Alternatives |
1st
week May 2002 – 2nd week October 2002 |
|
Task 7 - Prototype Site Plans |
1st
week May 2002 – 4th week October 2002 |
|
Task 8 - Delivery of Work Products
& Executive Summary |
|